This item was considered after item nine on
the agenda.
4.1 David Walton (Community
Assets Manger) introduced the report; the following key points were
noted:
- An internal audit in April 2014 had
highlighted changes required to the monitoring of the leisure
contract. These changes had been implemented and the new system was
reflected in the information provided in the report.
- The technical monitoring of the
contract had been outsourced.
- The Community Assets Manger was
responsible for monitoring service delivery.
- The financial performance of the
contract, in terms of the provider’s profits and losses was
of less importance than the delivery of quality services to
residents.
- The contract cost was approximately
eight or nine per cent of the cost of running the leisure centres.
The contractor was responsible for generating income through the
development of the service.
- Providers were forecasting profit
overall, although there may be losses in parts of the year;
dependent on fluctuations in demand.
- In the future, the contract should
enable the provider to pay Lewisham for the delivery of the
service.
- There would be a benchmarking
exercise at year seven of the contract (if the contractor met the
conditions within the contract to be able to call it).
- The exercise would determine whether
the initial income and expenditure projections were still valid.
Benchmarking exercises would take place every five years following
the initial term.
- The contract had been running for
three and a half years.
4.2 David Walton (Community
Assets Manager); Matt Henaughan (Community Resources Manager) and
Liz Dart (Head of Culture and Community Development) responded to
questions from the Committee, the following key points were
noted:
- Projections for income and
expenditure had been developed at the beginning of the contract; so
it was expected that there would be variances in the levels of
income projected and attained from month to month.
- The original budgets allocated might
not have been applicable to the current circumstances.
- There were some areas of spending
which appeared to have increased by significant amounts.
- Changes in expenditure and income
from month to month could be explained by the difference between
four and five week months, as well as the allocation of costs and
supplies from one month to another.
- Losses would be envisaged in the
winter months for swimming. The costs of maintaining and staffing
the pool remained the same as the rest of the year but there was a
lot less income.
- There was still a limited
communications budget – but this was not as much as the
budget available at the beginning of the contract.
- The Be Active programme (which
provided free or subsidised use of leisure centres for specified
groups) was popular – but not profitable.
- Wavelengths was primarily a swimming
focused centre, which would not be expected to generate high levels
of profit.
- Lifecycle works were taking place at
the Bridge.
- The gym should be completed by 13
March, when works to the sports hall would begin.
- Work would also take place to
refurbish the toilets and the dry change facilities.
- There would also be less noticeable
changes, including repairs to the swimming pool pump and the air
handling system.
- There would be a re-launch of the
facilities following the completion of the works. Councillors would
be notified when this was taking place.
- Lifecycle costs were included within
the current contract costs- with spending guided by the original
condition reports available at the start of the tender
process.
- Once the works had been completed,
the contractor would be expected to maintain the facilities in good
condition.
- The Council was monitoring the
contract closely in advance of the benchmarking exercise. Officers
would work to negotiate the best possible outcome.
- The management fee for the 1Life
contract was paid through the PFI (Private Finance Initiative)
contract.
4.3 The Committee also
discussed the possibility of making an unannounced visit to a
leisure centre in the future.
Resolved: that the report be noted.