Decision:
Having considered an officer report, and presentations by the Chair of the
Overview & Scrutiny Committee, Councillor Alan Hall and by the Cabinet
Member for Resources, Councillor Paul Maslin, the Mayor agreed that
(i) the comments of the Public Accounts Select Committee of 16 December 2013, incorporating the views of the respective select committees be received;
|
(ii) the previously agreed savings package of £17.0m be amended and referred to Council following an officer review which identified that circa £0.7m of these proposals were no longer achievable, meaning that the previously agreed package of savings for 2014/15 is revised down to just over £16.2mas detailed in Appendix A;
|
(iii) revenue budget savings of £6.258m be approved, of which £5.658m relates to 2014/15 and £0.6m relates to 2015/16, as detailed in Appendix E; subject to saving CYP13 being rejected and saving CYP12 being deferred;
|
(iv) the supporting report and recommendations for CYP12, the Attendance and Welfare service be deferred to the February 12 meeting to allow pre-decision scrutiny by the Children & Young People Select Committee on January 29 2014; and
|
(v) additional efficiency savings of £2.5m, as set out in section 6.2 be approved. |
Minutes:
The report was presented by the Cabinet Member for Resources, Councillor
Paul Maslin who highlighted measures taken to achieve savings required for
what he believed to be the Government’s failing austerity policy.
The Executive Director for Resources and Regeneration’s representative then
reported and advised all savings would be fed into the Budget in February
2014.
The Mayor reported that he had attended the Public Accounts Select
Committee two days previously and had promised to withdraw saving CYP12
from consideration to allow pre decision scrutiny by the Children and Young
People Select Committee.
Councillor Alan Hall then addressed the Mayor as Chair of the Overview &
Scrutiny Committee and on behalf of the Labour Group. He commented on
specific savings as follows:
COM03 He advised future increases in voluntary sector funding might be
required as part of a restructuring of public services.
CUS07 He said the Overview & Scrutiny Committee would examine the
saving in greater detail the following evening.
CYO5 Staff consultation would be welcomed.
CYP12 Further pre decision scrutiny was supported.
CYP13 He believed the saving was premature.
CUS03 Further discussion on improvements to recycling collection was
required.
R&R02 Benchmarking results should be subject to the scrutiny process.
COM01 A large piece of work should be addressed in the round in the
Lewisham Futures programme.
The Mayor then considered each saving individually as follows:
CYP01 Approved
CYP03 Approved
CYP04 Approved
CYP05 Approved with the Mayor expressing concern that consultation
with staff had not been completed and stated if issues emerged
they should be reported to him.
CYP06 Approved
CYP07 Approved
CYP08 Approved
CYP09 Approved
CYP010 Approved
CYP11 Approved
CYP12 Deferred
CYP13 Rejected, as the Mayor was not persuaded it was sensible to
take a saving from a service recently restructured and still
bedding down.
CYP14 Approved
CYP15 Approved
COM01 Approved and the comments of the Chair of Overview &
Scrutiny be noted for future years.
COM02 Approved with the Mayor noting this effectively represented a
grant substitution.
COM03 Approved
COM04 Approved
CUS01 Approved
CUS02 Approved
CUS03 Approved, with the Mayor receiving an assurance from the
Executive Director for Customer Services that he would discuss
the issues involved with the chief executives of Registered
Social Landlords.
CUS04 Approved
CUS05 Approved
CUS06 Approved
CUS07 Approved, with the Mayor noting representations received from
the Housing Select Committee and Unison and asking for
reassurance that the saving was possible and about the
capacity of current providers.
CUS08 Approved with the Mayor expressing concern that consultation
with staff had not been completed and stated if issues emerged
they should be reported to him.
R&R01 Approved
R&R02 Approved with the Mayor receiving a tabled paper from the
Public Accounts on comparative charges made by other
boroughs and receiving an undertaking from the Executive
Director for Resources and Regeneration that the methodology
in determining supermajor costings would be provided
subsequent to the meeting.
R&R03 Approved
R&R04 Approved
Having considered an officer report, and presentations by the Chair of the
Overview & Scrutiny Committee, Councillor Alan Hall and by the Cabinet
Member for Resources, Councillor Paul Maslin, the Mayor, for the reasons set
out in the report subject to the variations outlined above, agreed that
(i) the comments of the Public Accounts Select Committee of 16 December 2013, incorporating the views of the respective select committees be received;
|
(ii) the previously agreed savings package of £17.0m be amended and referred to Council following an officer review which identified that circa £0.7m of these proposals were no longer achievable, meaning that the previously agreed package of savings for 2014/15 is revised down to just over £16.2mas detailed in Appendix A;
|
(iii) revenue budget savings of £6.258m be approved, of which £5.658m relates to 2014/15 and £0.6m relates to 2015/16, as detailed in Appendix E; subject to saving CYP13 being rejected and saving CYP12 being deferred;
|
(iv) the supporting report and recommendations for CYP12, the Attendance and Welfare service be deferred to the February 12 meeting to allow pre-decision scrutiny by the Children & Young People Select Committee on January 29 2014; and
|
(v) additional efficiency savings of £2.5m, as set out in section 6.2 be approved. |