Agenda item
Update on plans for the Bakerloo line, DLR and Overground
Decision:
Resolved: to note the report – and to
recommend that the committee retains its focus on rail
infrastructure in 2014/15.
Minutes:
Simon Moss (Transport Policy
and Development Manager) introduced the report; the following key
points were noted:
- The report provided
an update on the Docklands Light Railway (DLR), Overground and
Bakerloo line but it was unlikely that Lewisham would get all three
rail improvements.
- Over the past year
there had been concurrent studies by Transport for London
(TfL) looking at the feasibility of
extending the DLR and Bakerloo line.
- Officers were
concerned about potential plans to extend the DLR through the
borough- because the extension would not fit alongside existing
infrastructure – and had the potential to create substantial
disruption as it passed through the borough. For example, one
version of the proposals would take the line through Ladywell
fields, which would be unacceptable.
- It was also clear
from TfL’s DLR feasibility
studies that the benefit cost ratio was likely to be too low to
make the case for the extension.
- The ratio was
estimated to be less than 1 – meaning for every pound spent
there would be less than one pound in benefits generated. As a
minimum requirement a viable transport scheme should have a ratio
of more than two.
- The Mayor of Lewisham
had written to the Mayor of London to express disappointment at the
findings of the DLR study – and to reiterate the
borough’s interest in the extension of the London Overground
via Lewisham.
- It was most likely
that the extension of the Bakerloo line would take over the Hayes
line – freeing up capacity for the Overground to operate via
Lewisham.
- It was recognised
that there was insufficient capacity at Lewisham at present to
extend the Overground, therefore, any
Overground extension would need to be combined with an extension of
the Bakerloo line.
- The Bakerloo line had
a cost benefit ratio of 3.5. It was a more expensive project than
the Overground but this was a healthy ratio.
- The extension of the
Bakerloo line would be estimated to create more than £7.5B
pounds of benefits as a result of its £2B cost.
- There were reasons
for optimism; however, there were also a number of unresolved
issues.
- Primarily, it was not
clear how any spare capacity created at Lewisham station would be
used. The space would be valuable and all parties involved would be
keen to utilise it.
In response to questions from
the Committee, the following key points were noted:
- The cost benefit
ratio of the Bakerloo line extension had substantially increased in
the time since the Committee had last considered the issue. It was
not clear why this was the case – but it was likely that is
was a result of changing demographics and assumptions about future
regeneration in the borough.
- There were no
immediate plans to commission further feasibility work from
consultants.
- LB Bromley was
committed to the extension on the DLR- but it was recognised that
there were significant limitations which would need to be addressed
in order to make it feasible.
- In its current form,
with the low cost benefit ratio, the extension of the DLR was not
feasible.
- There was a strong
case for the extension of the Bakerloo line. However, an Overground
extension would be quicker and cheaper to deliver.
- There would need to
be a commitment to extending the Bakerloo line before the borough
could commit to an Overground extension. This might involve
building a new station to the south of the town centre.
- It was recognised
that the ‘Catford loop’ line was poorly served.
Officers were not able to rule out the potential of using the line
for the Bakerloo line.
- The DLR could not use
ordinary rail track – and this ruled out the option of
allowing he DLR to take over the Hayes Line.
- It wasn’t yet
clear where any future Overground extension would start and finish.
Lewisham would not, however, want to lose its connection to central
London.
- Councillors could be
involved in all stages of the planning process. Officers would
return to the committee on a regular basis to provide updates,
information and advice on developments.
Resolved: to note the report – and to
recommend that the committee retains its focus on rail
infrastructure in 2014/15.
Supporting documents: