New Homes Programme Update – Bampton Estate part 2

Meeting: 05/06/2019 - Mayor and Cabinet (Item 73)

New Homes Programme Update – Bampton Estate part 2

Additional documents:

  • Restricted enclosure 2

Decision:

Having considered a confidential officer report, and a presentation by the

Cabinet Member for Housing, Councillor Paul Bell, the Mayor and Cabinet

agreed that:

 

(1) the revised scheme has reduced costs compared with the previous

application and the scheme has a stated positive NPV;

 

(2) the cost for the architects and other professional services required to

submit a revised scheme was approved in the 2nd PID report submitted in

February 2019 with the PID not covering the Post-Contract programme costs,

fees or any works including detailed design and build of the homes.

 

(3) the revised scheme which retains 19 Bampton Road negates the need to

purchase from L&Q and demolish 19 Bampton Road (stated sale price plus all

associated legal/valuation costs and demolition).

 

(4) the revised scheme provides 39, 1-bedroom social rent housing units and

these are to be let at London Affordable Rent (LAR) levels and the scheme

appraisal assumes a stated LAR rental income of per unit, per week plus

service charge;

 

(5) a decision by Mayor and Cabinet on 11 July 2018 approved a construction

budget for the Bampton scheme. 

 

(6) Parts 1 (public) and 2 (closed) of this item be jointly considered in order to

reach a decision on whether to progress the revised scheme to planning. 

Minutes:

Having considered a confidential officer report, and a presentation by the

Cabinet Member for Housing, Councillor Paul Bell, the Mayor and Cabinet

for the reasons set out in the report by a vote of 7-0:

 

RESOLVED that:

 

(1) the revised scheme has reduced costs compared with the previous

application and the scheme has a stated positive NPV;

 

(2) the cost for the architects and other professional services required to

submit a revised scheme was approved in the 2nd PID report submitted in

February 2019 with the PID not covering the Post-Contract programme costs,

fees or any works including detailed design and build of the homes.

 

(3) the revised scheme which retains 19 Bampton Road negates the need to

purchase from L&Q and demolish 19 Bampton Road (stated sale price plus all

associated legal/valuation costs and demolition).

 

(4) the revised scheme provides 39, 1-bedroom social rent housing units and

these are to be let at London Affordable Rent (LAR) levels and the scheme

appraisal assumes a stated LAR rental income of per unit, per week plus

service charge;

 

(5) a decision by Mayor and Cabinet on 11 July 2018 approved a construction

budget for the Bampton scheme. 

 

(6) Parts 1 (public) and 2 (closed) of this item be jointly considered in order to

reach a decision on whether to progress the revised scheme to planning.