Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
Having considered a confidential officer report and a presentation by the
Cabinet Member for School Performance, Councillor Chris Barnham, the
Mayor and Cabinet for the reasons set out in the report by a vote of 9-0:
RESOLVED that:
(1) the tender process recently undertaken for the New Woodlands school
remodelling project be noted;
(2) the revised programme for delivery of the project be noted;
(3) an increase in the overall project budget by a stated sum be approved in
light of the revised timescales and phased approach to the project set out;
(4) the award of a construction works contract to Savoy Developments Ltd
for a stated contract value be approved to complete phase 2 of the
remodelling works at New Woodlands school project; and
(5) a variation to the Tibbald Campbell Reith multi-disciplinary consultancy
contract be approved increasing the stated total value.
Publication date: 25/04/2019
Date of decision: 24/04/2019
Decided at meeting: 24/04/2019 - Mayor and Cabinet
Accompanying Documents: