Menu
Council meetings

Decision details

Contract Award Report New Woodlands School

Decision status: For Determination

Is Key decision?: Yes

Is subject to call in?: No

Decisions:

Having considered a confidential officer report and a presentation by the

Cabinet Member for School Performance, Councillor Chris Barnham, the

Mayor and Cabinet for the reasons set out in the report by a vote of 9-0:

 

RESOLVED that:

 

(1) the tender process recently undertaken for the New Woodlands school

remodelling project be noted;

 

(2) the revised programme for delivery of the project be noted;

 

(3) an increase in the overall project budget by a stated sum be approved in

light of the revised timescales and phased approach to the project set out;

 

(4) the award of a construction works contract to Savoy Developments Ltd

for a stated contract value be approved to complete phase 2 of the

remodelling works at New Woodlands school project; and

 

(5) a variation to the Tibbald Campbell Reith multi-disciplinary consultancy

contract be approved increasing the stated total value.

Publication date: 25/04/2019

Date of decision: 24/04/2019

Decided at meeting: 24/04/2019 - Mayor and Cabinet

Accompanying Documents: