Having considered an officer report, and a presentation by the Mayor, the
Mayor and Cabinet agreed that:
(1) the progress of the Heathside and Lethbridge Regeneration
Scheme and the current position in relation to Phases 5 and 6 as set out be
noted;
(2) the increase in the number of new homes from the original master plan
and that the scheme will now be 52% affordable (by habitable rooms) be
noted; and
(3) the proposed Phase 5 and Phase 6 Project Briefs on the basis set out be
approved.