Menu
Council meetings

Agenda item

Written Updates: transport, new developments, Station Approach

Minutes:

7.1    Cllr Curran directed attendees to the pack of written updates that was provided.

 

7.2    Transport issues

 

Bakerloo Line Extension
 
TfL gave an update on Sept 7 2015 - To see the details of this update please go to the TfL website at:
 

https://consultations.tfl.gov.uk/tube/bakerloo-extension?cid=bakerloo-extension

 

Update - 7 September 2015
We have today published the Responses to Issues Raised document. Details of the consultation can be found below.

Between 30 September and 7 December 2014, a consultation was held on extending the Bakerloo line from Elephant & Castle station through Southwark towards Lewisham, Bromley and Hayes. Thank you to all those who took part in this consultation.

More than 15,000 responses were received from members of the public and stakeholders offering their views on the extension’s proposals. Overall, there was a very high level of support for the principle of an extension to the Bakerloo line. More than ninety five percent or responses expressed support for the principle of extending the Bakerloo line.   

 

What Happens Next

The consultation responses included suggestions regarding a number of alternative routes. We are now reviewing these options further. Once the options have been fully explored a further public consultation is anticipated in 2016.  This consultation will be able to present the extension proposals in more detail.


We are also working on responding the key issues raised within the consultation, with an aim to publish this report later in 2015.

If a decision is made to progress the scheme, and the necessary funding secured, it is anticipated that construction could commence in around 2023 and be completed in approximately 2030.

 
Terminating at Lewisham

We are also considering options for where the extension may end. An extended Bakerloo line terminating at Lewisham would cost less and focus on supporting inner London’s growth and regeneration. It would also support growth and regeneration in the northern parts of the Borough of Lewisham.
 
Extending the line beyond Lewisham (to Beckenham Junction and Hayes)
If the proposed Bakerloo line extension runs as far as Hayes, it would replace the existing National Rail line between Lewisham and Hayes. It would also utilise the current link to Beckenham Junction. A Tube stop at Beckenham Junction would be in addition to the National Rail station at this location.
Currently, six trains per hour use the Hayes line to London Bridge. An extended Bakerloo line to Hayes could mean up to 15 trains per hour could serve this route. It also means that up to 50 per cent more people may be able to use the line to access central London and the Docklands - via DLR at Lewisham.


This substantial capacity increase would support growth around stations in locations such as Catford. In addition to capacity increases, an extension beyond Lewisham would relieve crowding on the South Eastern Rail network. This is because trains paths that currently go to London Bridge from Hayes could be reallocated to other routes between central London and the southeast.


A proposed extension to Hayes means that people who currently travel on the Hayes line into London Bridge and Cannon Street would need to change from the Bakerloo line to directly reach these destinations. However, an extended Bakerloo line would also provide direct connections from Hayes to other parts of central London including Waterloo, Piccadilly Circus, Oxford Circus and Paddington.
 

Possible extension to Bromley town centre
As part of extending the Bakerloo line beyond Lewisham, there is the possibility of continuing east, in a new tunnelled section, to Bromley town centre. A new direct link between central London and this major centre would support the area’s economy and housing growth. It would also provide a new link between central London and Bromley, as well as connections to Canary Wharf via Lewisham.
 
Funding the extension
The cost of extending the Bakerloo line, as far as Hayes, is currently estimated between £2 and £3 billion. As part of our next phase of work, we will work with the London boroughs, through which the proposed extension would run, to identify possible options for project funding.
 
As has been the case for other major infrastructure projects (such as Crossrail and the Northern Line Extension), any funding package is likely to include contributions from new residential and commercial developments along the proposed extension.This means that in order for the Bakerloo line extension to be progressed, further development along the proposed route is required. It is unlikely the extension can happen without this new development.
 

Additional information

A southern extension of the Bakerloo line has been under consideration from the time the line was first opened in 1906. We have reviewed other options for improving transport in southeast London over the last few years.

A summary of this work is available in our Background report.

https://consultations.tfl.gov.uk/tube/bakerloo-extension/user_uploads/bakerloo-line-extension---background-to-consultation---amended.pdf

 

AMENDMENT TO DOCUMENT (7/11/2014): Paragraph 4.1.6. of the Background report linked to above was updated on 7 November 2014. The changes to the wording are to clarify that extensions of Tramlink are still being considered by TfL but not in the context of an alternative to the Bakerloo line extension scheme proposed in this consultation. The changes to this paragraph are for clarification only and do not introduce any new or additional information affecting the consultation exercise.

 
Given the project’s potential impacts on National Rail services, we are working closely with Network Rail on the proposed project. Network Rail has included a proposal to extend the Bakerloo line as part of their London and South East Route Utilisation Strategy (2011)

London Bridge

 

Update on current works

Over Bank Holiday weekend works included the laying of more than 1km of new track, the installation of a massive new signal gantry near Waterloo East, several new sets of points installed and more than 6km of power cables laid. 

Since then the first ballast and rails arrived this weekend so the Thameslink Programme can begin laying track across Borough Viaduct, in central London. This viaduct will be used by Charing Cross trains from January 4, 2016, while the old viaduct is re-laid to carry future Thameslink services.

 

Sydenham Road

The new contractor has now confirmed dates for signal linking all works on Sydenham Road by end of October.

 

7.3 The Greyhound Update

 

Purelake commenced building works on 11 May 2015.

 

Building Control officers have conducted frequent site visits to inspect the works being undertaken. Officers have advised that since the recommencement of works, 2-3 workmen have generally been present on site.

 

More recently there has been a lull in building activity, however there have been some sightings of workmen and deliveries of materials over the last week or so.

 

There has been work on the timber frame of the new roof and three chimney stacks have been built. There have been recent deliveries of roofing tiles for the project.

 

The former gable ends to the front have been taken down due to severe

cracking and leaning. The bricks were taken down by hand, and have been stacked prior to the eventual reconstruction of the gables.

 

The existing lintels that are cracked beyond repair. A suitable replacement will be sourced by the developers that will be of a similar appearance to the existing ones.

 

Q.   Pat Trembath from the Sydenham Society asked if the progress with The Greyhound was included in the agenda for the Mayor & Cabinet Meeting for 30th September.

 

A.   Cllr Best confirmed that it would be included and Sarah agreed to provide the latest update as an appendix to these minutes.

 

 

7.4 Sydenham Update  

 

Existing Issue        

 

The toilets in Sydenham Station Approach were vandalised and the manufacturer has made the repair. The fence to the rear of the toilet is now installed. The water metre works were finished yesterday (16th September) and the toilet is now fully operational.

 

 Network Rail have repaired the loose coping stone.

 

Riney's are due to start installing the studs to the forecourts today (17th September) This work should be finished next week.

 

Riney's are unclear of the location of the notice board and we are still awaiting a date for the painting of the water pump. We will continue to chase outstanding works.

 

The railing for outside the post office should be installed by November.

 

Newly Reported Issue

 

Girton Road Car Park

 

Cars were badly parked obstructing vehicles from entering the main body of the car park; also cars entering "the lanes" the wrong way.   The white lines for bays / arrows in both the top & lower car park needs repainting, with a couple of no parking yellow boxes in certain places to prevent cars causing an obstruction.

 

This has been organised and repainting will take over the next week, weather permitting.         

 

Damage occurred to paving slab in Venner Square after work by the Water Board and the finish is uneven. We will report back on progress.

 

Station Approach Toilets- The toilets are now open.

 

Appendix 1

 

Greyhound Update 30.09.15 from minutes of Mayor and Cabinet Meeting

 

The Greyhound Update

(extract from minutes of Mayor & Cabinet Meeting 30 09 15)

 

 

6. Current Position

 

Officers advised at Mayor and Cabinet on July 15 2015 that works up to that

time had concentrated upon the reconstruction of the timber frame of the new

roof, together with the rebuilding of three chimney stacks and the front gables.

These have since been rebuilt and inspected by Planning, Conservation and

Building Control officers, who are satisfied with the standard of works

undertaken.

 

Two or three workers have generally been on site since works began in May,

and this is expected to increase during the concluding period of construction.

In August however, external works ceased, and no workers were evident. The

developer has since advised that a worker was present within the ground floor

area of the building, and was measuring, cutting and treating original barge

boards and rafters. In addition, the delivery of the central roof truss was being

awaited, which arrived during the week beginning 17th  August. This has since

been installed, and works to complete the roof recommenced.

 

During the week beginning 31stAugust, slate tiles were delivered to the site for installation, however the developer considered these to be of poor quality and were subsequently returned. At the time of writing this report, a further delivery of tiles was being awaited, which will take approximately 2 weeks.

 

Once the roof is secure and watertight, works will then commence on the

lower levels. The unauthorised timber mezzanine floor that can be seen from

the public realm through the first floor window openings remains in situ. The

developers have reiterated the floor will be removed once the roof is complete. Building Control remain satisfied that the eventual removal of the floor is unlikely to compromise the integrity of the structure.

 

To date, the existing lintels that are cracked beyond repair have not been

replaced. A suitable replacement is currently being sourced by the developers

that will be of a similar appearance to the existing. Officers will inspect the new lintels once they arrive on site.

 

The new and repaired ‘drinking corridor’ tiles have been delivered to the

developers, and are currently in storage at their offices.

 

A schedule of works setting out timescales of the redevelopment has not been afforded to officers, however the developer has indicated that external works listed in Paragraph 5.1.8 are likely to be completed between late October and mid November 2015. Whilst this is considerably later than the original intention to complete in September, considering the complexity of the roof construction - which has been confirmed by Building Control officers - the reason for the delay is reasonable.

 

Building Control have regularly visited the site and made contact with the

developers, and they consider the works undertaken to be in compliance with

the approved Building Regulations plans.

 

Planning and Conservation officers will also continue to monitor works by way

of regular site inspections and dialogue with the developers and their planning

agent.

 

 

Current Planning Application

 

In May 2015, a planning application was submitted by Purelake proposing the

construction of an extension to the western side of the building, and the formation of external stairs down to the basement located at the rear. Further information relating to the detailing of the proposed conservatory has been requested by officers. The application is due to be determined in November.

 

 

Schedule 10 Compliance

 

Schedule 10 of the S106 Agreement requires that the Owner notify the Council two months prior to the date of Practical Completion of the Restoration and Refurbishment Works’, the ‘Reinstatement Works’ and the New Public Realm Works. Officers will on receipt of such notification arrange to meet with the developer on site to determine whether the operations undertaken are satisfactory and in compliance with the agreed works. Schedule 10 paragraph 1.5 requires the construction and completion of those works in accordance with the details that have been approved by the Council.

 

In respect of the New Public Realm Works the approved S96a application proposed the following;

 

Bradstone Panache concrete paviors - silver grey and black finish;

• The planting of six Silver Birch trees;

• Victorian style lamp-posts painted black;

• Seating area;

• Secure cycle parking.

 

Officers considered the proposed public realm works to be acceptable.

Schedule 10 paragraph 1.3.1 requires the Owner to submit a Maintenance

Plan in respect of the New Public Realm Works, to the Council two months

prior to the date of Practical Completion. The Maintenance Plan is defined in

the S106 as a plan to secure the maintenance of the New Public Realm Works and which also ensures public access at all times.

 

Schedule 10 paragraph 1.4 requires the submission of a Shared Amenity Space Maintenance Plan to the Council two months prior to the date of Practical Completion. That plan is defined in the S106 as a plan to secure the maintenance and upkeep of the Shared Amenity Space being the amenity space provided as part of the Development and shown on Plan 4 attached to the S106. The submission of these details are currently being awaited.

 

Confirmation of full compliance with Schedule 10 will be confirmed in writing when the local planning authority is satisfied that the Restoration and Refurbishment Works, the Reinstatement Works and the New Public Realm Works have been completed in accordance with the details approved by the Council.