Having considered an open officer report, and a presentation by the Mayor,
the Mayor and Cabinet agreed that:
(1) the acceptance by the Council of £69.945 million in grant funding from the
GLA through the AHP 2021-26 be approved;
(2) authority be delegated to the Executive Director for Housing, Regeneration
and Public Realm in consultation with the Executive Director for Corporate
Resources and Director of Law, Governance and Elections to approve the
terms of and to enter into the grant agreement for the AHP 2021-26
programme funding;
(3) authority be delegated to the Director for Inclusive Regeneration to
substitute, amend and reconfigure the schemes within the AHP 2021-2026
programme, subject to remaining within the financial parameters of the AHP
2021-26;
(4) authority be delegated to the Director for Inclusive Regeneration to
authorise the submission of a further bid through the Continuous Market
Engagement (CME) process for the AHP 2021-26 for a minimum of a further
58 social rented homes, subject to the said bid being within the Building for
Lewisham agreed financial hurdles and parameters;
(5) £550,000 of S106 funds be allocated to the Achilles Street Regeneration
Project; and
(6) all schemes referenced shall come forward to subsequent Mayor and
Cabinet meetings for their necessary approvals as the projects progress.
Minutes:
Having considered an open officer report, and a presentation by the Mayor,
the Mayor and Cabinet for the reasons set out in the report and by a vote of
6-0:
RESOLVED that:
(1) the acceptance by the Council of £69.945 million in grant funding from the
GLA through the AHP 2021-26 be approved;
(2) authority be delegated to the Executive Director for Housing, Regeneration
and Public Realm in consultation with the Executive Director for Corporate
Resources and Director of Law, Governance and Elections to approve the
terms of and to enter into the grant agreement for the AHP 2021-26
programme funding;
(3) authority be delegated to the Director for Inclusive Regeneration to
substitute, amend and reconfigure the schemes within the AHP 2021-2026
programme, subject to remaining within the financial parameters of the AHP
2021-26;
(4) authority be delegated to the Director for Inclusive Regeneration to
authorise the submission of a further bid through the Continuous Market
Engagement (CME) process for the AHP 2021-26 for a minimum of a further
58 social rented homes, subject to the said bid being within the Building for
Lewisham agreed financial hurdles and parameters;
(5) £550,000 of S106 funds be allocated to the Achilles Street Regeneration
Project; and
(6) all schemes referenced shall come forward to subsequent Mayor and
Cabinet meetings for their necessary approvals as the projects progress.