Broadway Theatre Works part 1

Meeting: 13/01/2021 - Mayor and Cabinet (Item 420)

420 Broadway Theatre Works (part 1) pdf icon PDF 68 KB

Additional documents:

Decision:

Having considered an officer report, and a presentation by the jobshare

Cabinet Member for Culture, Jobs & Skills, Councillor Andre Bourne, the

Mayor and Cabinet agreed that:

 

(1) an open procurement exercise be approved to find a suitable Principal

Contractor for the proposed works to the Broadway Theatre, at the

approximate value set out in section one of the Part 2 report, and using the

process set out in section six of the open report; and

 

(2) officers be authorised to continue to utilise the services of Purcell as Lead

Consultant for RIBA stages 3-7 via direct call-off from the Fusion 21

Framework and to award a further contract to Purcell at a cost of £607,605.

Minutes:

Having considered an officer report, and a presentation by the jobshare

Cabinet Member for Culture, Jobs & Skills, Councillor Andre Bourne, the

Mayor and Cabinet, for the reasons set out in the report and by a vote of 10-0,

 

RESOLVED that

 

 (1) an open procurement exercise be approved to find a suitable Principal

Contractor for the proposed works to the Broadway Theatre, at the

approximate value set out in section one of the Part 2 report, and using the

process set out in section six of the open report; and

 

(2) officers be authorised to continue to utilise the services of Purcell as Lead

Consultant for RIBA stages 3-7 via direct call-off from the Fusion 21

Framework and to award a further contract to Purcell at a cost of £607,605.