The report was presented by Councillor Paul Bell who received confirmation

from Councillor Jonathan Slater that the local Councillors supported the

proposals

 

Having considered an open officer report, and a presentation by the Cabinet

Member for Housing, Councillor Paul Bell, the Mayor and Cabinet, for the

reasons set out in the report by a roll call vote of 10-0:

 

RESOLVED that:

 

(1) the progress of the Excalibur Estate Regeneration Scheme as set out be

noted;

 

(2) the rationale be noted for including the land at the former Tenant

Management Organisation (TMO) office at 1 Baudwin Road and neighbouring

property at 3 Baudwin Road in conjunction with the Excalibur Estate

Regeneration Scheme;

 

(3) the inclusion of the land at the former TMO office at 1 Baudwin Road and

neighbouring property at 3 Baudwin Road in conjunction with the Excalibur

Estate Regeneration Scheme be approved;

 

(4) Subject to agreement of the above recommendation and the Phase 3 land

being transferred to L&Q, the transfer be approved of the land at 1 & 3

Baudwin Road to L&Q for development subject to the development  of Phase

3 going ahead;

 

(5) Subject to agreement of the above recommendation, authority be

delegated to the Executive Director for Housing, Regeneration and

Environment in conjunction with the Director of Law to negotiate and enter

into a legally binding agreement with L&Q requiring the land of 1 and 3 Baudwin Road to be used to deliver 3x2 and 1x3 bedroom houses to be let at social rent; and