Heathside and Lethbridge Phases 5 & 6 Land Assembly

Meeting: 08/05/2019 - Mayor and Cabinet (Item 50)

50 Heathside and Lethbridge Phases 5 & 6 Land Assembly pdf icon PDF 67 KB

Additional documents:

Decision:

Having considered an officer report, and a presentation by the Mayor, the

Mayor and Cabinet agreed that:

 

(1) the progress of the Heathside and Lethbridge Regeneration

Scheme and the current position in relation to Phases 5 and 6 as set out be

noted;

 

(2) the increase in the number of new homes from the original master plan

and that the scheme will now be 52% affordable (by habitable rooms) be

noted; and

 

(3) the proposed Phase 5 and Phase 6 Project Briefs on the basis set out be

approved.

Minutes:

Having considered an officer report, and a presentation by the Mayor, the

Mayor and Cabinet for the reasons set out in the report by a vote of 6-0:

 

RESOLVED that:

 

(1) the progress of the Heathside and Lethbridge Regeneration

Scheme and the current position in relation to Phases 5 and 6 as set out be

noted;

 

(2) the increase in the number of new homes from the original master plan

and that the scheme will now be 52% affordable (by habitable rooms) be

noted; and

 

(3) the proposed Phase 5 and Phase 6 Project Briefs on the basis set out be