Decision:

Having considered an officer report and a presentation by the Cabinet

Member for Community Sector, Councillor Jonathan Slater, the Mayor and

Cabinet agreed that:

 

(1) an extension of the current contract between the Council and SELCHP Ltd

from its current expiration date of the 31st December 2023 until 30th June

2027 be approved being a contract for the provision of waste disposal via

incineration at the SELCHP facility;

 

(2) implementation of approval of this extension is dependent on approval

from the Royal Borough of Greenwich, as this is a joint contract between

Lewisham and Greenwich with SELCHP Ltd.

Minutes:

Having considered an officer report and a presentation by the Cabinet

Member for Community Sector, Councillor Jonathan Slater, the Mayor and

Cabinet, for the reasons set out in the report:

 

RESOLVED by six votes to nil that:

 

(1) an extension of the current contract between the Council and SELCHP Ltd

from its current expiration date of the 31st December 2023 until 30th June

2027 be approved being a contract for the provision of waste disposal via

incineration at the SELCHP facility;

 

(2) implementation of approval of this extension is dependent on approval

from the Royal Borough of Greenwich, as this is a joint contract between

Lewisham and Greenwich with SELCHP Ltd.

 