SELCHP Extension
Additional documents:
Decision:
Having considered an officer report and a presentation by the Cabinet
Member for Community Sector, Councillor Jonathan Slater, the Mayor and
Cabinet agreed that:
(1) an extension of the current contract between the Council and SELCHP Ltd
from its current expiration date of the 31st December 2023 until 30th June
2027 be approved being a contract for the provision of waste disposal via
incineration at the SELCHP facility;
(2) implementation of approval of this extension is dependent on approval
from the Royal Borough of Greenwich, as this is a joint contract between
Lewisham and Greenwich with SELCHP Ltd.
Minutes:
Having considered an officer report and a presentation by the Cabinet
Member for Community Sector, Councillor Jonathan Slater, the Mayor and
Cabinet, for the reasons set out in the report:
RESOLVED by six votes to nil that:
(1) an extension of the current contract between the Council and SELCHP Ltd
from its current expiration date of the 31st December 2023 until 30th June
2027 be approved being a contract for the provision of waste disposal via
incineration at the SELCHP facility;
(2) implementation of approval of this extension is dependent on approval
from the Royal Borough of Greenwich, as this is a joint contract between
Lewisham and Greenwich with SELCHP Ltd.
The meeting closed at 7.24pm