SEND Expansions
Additional documents:
Decision:
Having considered a confidential officer report and a presentation by the
Cabinet Member for Children & Young People, Councillor Paul Maslin, the
Mayor agreed that:
(1) the procurement route to be used in order to deliver the capital works for
the expansion of Watergate and Greenvale SEND schools be noted and that
officers are in the process of appointing a provider to undertake multi-
disciplinary services up to RIBA stage 6 for remodelling of New Woodlands;
(2) the indicative total budget to deliver the works be approved, on the
understanding a further report be presented for the award of the construction
contracts for Greenvale, Watergate and New Woodlands after the detailed
design stage is complete;
(3) officers be authorised to proceed with the procurement of the demolition of
the former Brent Knoll School building on Mayow Road, and authority be
delegated to the Executive Director for Resources and Regeneration to enter
into a contract for the works;
(4) authority be delegated to the Executive Director for Resources and
Regeneration to enter into a Pre-Construction Services Agreement for
Watergate and Greenvale forming stage one of the proposed two-stage
Design and Build process that will be used to deliver each scheme.
Minutes:
Having considered a confidential officer report and a presentation by the
Cabinet Member for Children & Young People, Councillor Paul Maslin, the
Mayor, for the reasons set out in the report:
RESOLVED that:
(1) the procurement route to be used in order to deliver the capital works for
the expansion of Watergate and Greenvale SEND schools be noted and that
officers are in the process of appointing a provider to undertake multi-
disciplinary services up to RIBA stage 6 for remodelling of New Woodlands;
(2) the indicative total budget to deliver the works be approved, on the
understanding a further report be presented for the award of the construction
contracts for Greenvale, Watergate and New Woodlands after the detailed
design stage is complete;
(3) officers be authorised to proceed with the procurement of the demolition of
the former Brent Knoll School building on Mayow Road, and authority be
delegated to the Executive Director for Resources and Regeneration to enter
into a contract for the works;
(4) authority be delegated to the Executive Director for Resources and
Regeneration to enter into a Pre-Construction Services Agreement for
Watergate and Greenvale forming stage one of the proposed two-stage
Design and Build process that will be used to deliver each scheme.