Decision Maker: Mayor and Cabinet
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
Having considered an open officer report, and a presentation by the Cabinet
Member for Housing, Councillor Paul Bell, the Mayor and Cabinet agreed that:
(1) Match-funding to the GLA Good Growth Fund in the sum of £1.65M be
approved to be funded from the Council’s General Fund Capital Programme;
(2) authority be delegated to the Executive Director for Housing, Regeneration
and Public realm in conjunction with the Director of Law to agree to the terms
of and enter into the GLA’s Good Growth Grant Agreement and to agree a
strategy and programme in conjunction with the GLA and to further
commence procurement of a suitable consultancy team to support the project
via the ADUP framework.
(3) The transfer of S.106 funding in the sum of £1,515,537, originally
proposed for the delivery of a footbridge between Doggett Road and the
Barratt’s development on the former Catford Greyhound Stadium site be
approved to deliver public realm and accessibility improvements to Catford
Stations as set out; and
(4) authority be delegated to the Executive Director for Housing, Regeneration
and Public Realm to agree the procurement strategy and appointment of a
suitable contractor to construct the Catford Stations scheme.