Having considered an open and a confidential officer report, and a

presentation by the Cabinet Member for Housing and Planning, Councillor

Paul Bell, the Mayor and Cabinet agreed that:

 

(1) the allocation of funding be approved and Lewisham Homes appoint a

contractor once the procurement process is complete to deliver construction

works for 5 new homes at the scheme known as Elderton Road Garages at a

scheme cost indicated in Part 2;

 

(2) Subject to planning permission being granted, the allocation of funding be

approved and Lewisham Homes appoint a contractor once the procurement

process is complete to deliver construction works for 5 new homes at the

scheme known as Walsham Road Garages at a scheme cost indicated in Part

2;

 

(3) Subject to planning permission being granted, the allocation of funding be

approved and Lewisham Homes appoint a contractor to undertake the

necessary enabling works for the Greystead Road development and support

investment works at a cost stated in Part 2; and

 

(4) authority be delegated to the Executive Director of Corporate Resources in

consultation with the Executive Director for Housing, Regeneration and Public

Realm and Director of Law, Governance and Elections, to agree the final

contract sum and Total Scheme Costs.