Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
Having considered an officer report, and a presentations by a Bellingham
Ward Councillor and by the jobshare Cabinet Member for Environment &
Transport, Councillor Sophie McGeevor, the Mayor and Cabinet agreed that:
(1) additional capital programme contribution of £1.936m be approved to
secure the investment;
(2) approval be given to begin the process of obtaining a traffic management
order for Beckenham Place Park, to enable the introduction of parking
enforcement;
(3) approval be given to grant a lease of the new education centre to the Field
Studies Council and responsibility be delegated to the Executive Director for
Customer Services, in consultation with the Assistant Director of
Regeneration and Place and the Head of Law, to agree final terms as set out.,
Publication date: 25/04/2019
Date of decision: 24/04/2019
Decided at meeting: 24/04/2019 - Mayor and Cabinet
Accompanying Documents: