Having considered a confidential officer report and a presentation by the
Cabinet Member for School Performance, Councillor Chris Barnham, the
Mayor and Cabinet for the reasons set out in the report and by a vote of 7-0:
RESOLVED that:
(1) the tender process undertaken for the Watergate and Greenvale school
expansion projects be noted;
(2) officers have completed the tender evaluation for the Greenvale project,
but will complete the Watergate evaluation early in the new year and provide
an update then;
(3) the revised programme for the Greenvale expansion project, and that
officers are currently procuring a demolition contractor to complete the site
preparation phase of the project, be noted;
(4) the overall project budget for the Greenvale expansion project be noted
and remains the same as the previously approved budget;
(5) the award of a Pre-Construction Services Agreement be made to Geoffrey
Osborne Limited for a stated contract value to complete Stage 1 of the
Greenvale expansion project, on the understanding that a further report will be
brought to Mayor & Cabinet to award the Stage 2 construction contract.