Officers confirmed that the expansion proposal would be subject to planning
permission being granted.
Having considered a confidential officer report, and a presentation by the
Cabinet Member for Children & Young People, Councillor Paul Maslin, Mayor
and Cabinet (Contracts) for the reasons set out in the report:
RESOLVED that:
(1) the award of a contract of works for a stated maximum value be made to
Engie Ltd (previously Keepmoat Regeneration Ltd), to facilitate the second
stage design and build delivery of a one form of entry expansion at Ashmead
Primary School, Ashmead Road, London SE8 4DX;
(2) the revised delivery budget for this scheme of a stated figure (including
fees and contingency) representing a stated approximate decrease on the
original stated budget agreed in March 2017.
(3) while planning permission is pending, approval under delegated authority
for an early works agreement wbe sought from the Executive Director for
Resources and Regeneration, for a value no greater than a stated amount
subsumed into the overall contract value once the contract is signed; and
(4) authority be delegated to the Executive Director for Resources &
Regeneration to negotiate final contract terms with Engie Ltd, within the
financial and other constraints set out.
The meeting closed at 6.05pm