5.1 Peter
North (Programme Manager, Sustainable Energy, Greater London Authority) introduced a presentation;
the following key points were noted:
- A third of
London’s CO2 emissions were generated by
heating.
- More energy was used
to heat buildings in the UK than was used for transport or
electricity generation. So in order to deliver reductions in
CO2, in buildings it would be necessary to increase the
energy efficiency of buildings and how the energy is
supplied.
- London had a target
of 60% reduction in 1990 levels of CO2 by 2025 alongside
a target to supply 25% of its energy from local decentralised
sources.
- The carbon content of
electricity generation would be an important part of future work in
this area.
- A public role was
required in order to enable district energy.
- There were three main
categories of decentralised energy projects: single sites utilising
small/medium CHP systems; multi-site mixed use schemes: area wide
transmission networks with extensive heat pipe systems.
- In 2011 the GLA
carried out a decentralised energy capacity study. It was found
that London had more capacity potential than the 25% target for
decentralised energy set by the Mayor.
- The London Plan
contains a range of specific policies to promote the development of
decentralised in new developments.
- Insulation was the
first and most important part of ensuring the efficient use of
energy.
- Generating energy
from renewables had proved difficult in the urban
environment.
- Densely developed
areas were the most suitable for decentralised energy
schemes.
- Area planning was an
important part of enabling the future connection of new
developments to existing networks.
- London boroughs could
be involved in the delivery of decentralised energy projects in a
number of different ways. They might choose to deliver their own
schemes, or they might only act as a planning authority,
facilitating delivery by others.
- Development of energy
master plans was a long process taking around six months from start
to finish, but work had taken place in 10 boroughs to achieve a
coordinated policy.
- The GLA’s EU
funded technical, commercial and financial advisory services had
helped develop a £300m pipeline of projects. The advisory
support was running down and the GLA are proposing a successor
arrangement that will operate until 2020.
- Two major projects
were- Gospel Oak Hospital, and Islington Heat and Power scheme, the
later connecting 850 dwellings providing 10% lower energy
bills.
- Phase two of the Islington scheme
sought to use waste heat from the underground and other
sources.
- There were four
energy from waste plants in and around the city, that could provide heat for tens of thousands
of homes.
- SELCHP was finally
providing heating to estates in Southwark after 15 years of
operation as a power-only energy from waste facility..
- The future of heat
networks would be to utilise heat lost from other processes - each
would require technical availability and economic case.
- In order to meet the
government’s carbon targets, decentralised energy and
communal heating would need to be part of the solution.
5.2 Peter
North (Programme Manager, Sustainability, GLA) responded to questions from the committee, the
following key points were noted:
- It was recognised
that residential units had periods of peak demand; schemes which
incorporated commercial units were able to sustain more consistent
demand.
- In order to
demonstrate commercial viability and bring in private sector money,
work had to be done to develop the economic case for decentralised
energy schemes.
- Projects had to be
configured to attract lending and sustainable rates of return for
investors.
- Councils could use
funds from public loans board, green investment bank, London green
fund to get projects started.
- There had been
anecdotal information of discontent about some schemes. The detail
of which was not available.
- Further analysis of
concerns and the associated costs would be required in order to
understand how these problems arose and how they might be avoided
in future.
- There had been some
work carried out to investigate problems with insulation levels of
pipework. The lack of effective insulation could lead to
overheating and excessive heat losses.
- There might be
different reasons for problems on different schemes –
requiring further work in different cases to understand the source
of the specific problem or range of problems.
- It was recognised
that the levels of fixed charges for some systems, which remained
in the summer months, despite reductions in usage, were of concern
on some schemes.
- The Housing
Association, A2 dominion had a good record of delivering communal
heating systems.
5.3 Robin
Feeley answered questions from the
Committee; the following key points were noted:
- L&Q had 2500
homes in Lewisham, including the new development at Loampit
Vale.
- The problems
identified were not with communal heating systems, but rather with
the ability of developers and housing associations to deliver high
quality.
- Developers were in a
position where they could walk away once the project had been
delivered.
- It was important that
housing associations demanded high quality from their construction
contracts; commissioning agents should be required to demonstrate
the effectiveness of the schemes being delivered.
- There had been two
years of ‘blind push’ to install heating systems, the
details of the maintenance and operation of these systems was now
being unravelled.
- 9 Combined heat and
power systems (CHPs) were not working due to low
demand.
- 3 year project to
look at demand and specification of existing systems.
- Average bills for
properties with communal heating systems indicated that they were
not always more affordable than traditional schemes.
- At Loampit Vale, for
example, there was a £365 standing charge for
heating.
- There was also the
concern that communal heating systems did not offer any choice for
tenants.
- The key to ensuring
the effective deployment of these systems was to agree a proper
technical specification, using a robust tendering
process.
- The cost of the
assessment and monitoring work should be built into the tendering
process.
- L&Q made no
profit on schemes.
5.4 Brian
Regan (Planning Policy Manager) advised the committee
that:
- Lewisham’s
policy was to ask for major schemes (with 10 units or above) to
consider the installation of a communal heating system.
5.5 Members
also discussed the issues raised; the following key points were
noted:
- Concerns about the
speed with which communal heating systems were being deployed,
despite signs that there were problems.
- The potential lessons
to be learnt from the issues at Heathside and Lethbridge, including
– the importance of good planning; technical expertise;
project and contract management.
5.6 Jonathan
Graham (Combined Heat and Power Association (CHPA)) introduced a
presentation. The following key points were noted:
- Transparency and
fairness should be the driving principles of decentralised energy
provision.
- District heat was
technology neutral; CHP was one means for providing heat to a
shared heating system, amongst others.
- Registered social
landlords and local authorities were leading the way in
implementing new heating systems.
- CHP provided 2% of UK
heat – and was not a new technology.
- However, CHP was
being deployed in new places.
- Communal heating
systems were popular across Europe.
- Communal heating
systems had been delivered in a number of places, and had a number
of benefits (such as reducing costs and tackling fuel poverty) when
they were done right.
- Reductions could be
shown in practice.
- UK was lucky to have
cheap natural gas – but this would not last – so
alternative sources of heating need to be found.
- There were problems
for all modern buildings, which were often the unintended
consequence of too much air tightness.
- Common challenges
included – network losses and overheating; poor value from
electricity generation, low build quality through value
engineering, poor communication between partners, and lack of
transparency for end users.
- The CHPA would work
to offer solutions where problems had been identified. There are
two different Code of Practice schemes being delivered in 2015.
There is the Code of Practice, developed jointly by CHPA and CIBSE,
and there is the Heat Customer Protection Scheme, which will be an
independently operated scheme.
- There should be
obligations on all parts of the supply chain to improve
performance.
- Heat customer
protection scheme, required heat to be sold directly to customers
– but the industry would build on the foundation to help
people supplied by an energy supply company.
- It was intended that
there would be transparency for customers on costs & customer
protection.
- Gas costs are not the
same as heat costs, boiler maintenance and replacement needed to be
taken into account.
- Information and
clarity are needed around costs and expenditure on the different
systems available.
- There was a working
communal heating system in Lewisham at The South East London
Combined Heat and Power plant (SELCHP), which provided an example
of the viability of decentralised energy schemes.
- The Heat Network Code
of Practice would soon be in effect, as well as a protection scheme
for users.
- In order to maximise
the benefits of communal heating and avoid future problems, all
parts of the system had to ensure that they were committed to
building and operating systems to a high standard.
Standing orders were suspended
until the completion of business.
5.7 Jonathan
Graham (Combined Heat and Power Association) responded to questions
from the Committee, the following key points were noted:
- The Combined Heat and
Power Association had over 90 members, ranging from industrial and
heat supply companies to local authorities, including Birmingham,
Nottingham and Southampton. The list was available on the CHPA
website.
- There was an impetus
to decarbonise heating.
- Communal heating
could be efficiently delivered, but this had not been consistent in
every case.
- The CHPA was
developing tools to ensure that there were not problems in the
future.
- New build
developments were different from the communal heating systems that
had been in development previously, new rules for insulation in
residential buildings and energy efficiency meant that there was an
inconsistent level of demand.
- GLA has previously
published that 500 is the minimum amount of units to make a system
viable. But this was dependent on whether or not a commercial
approach to development was being taken.
5.8 Members
also discussed the issues raised and noted that: it appeared as
though there were sectional interests at every part of the communal
heating supply chain, including glazers, boiler engineers, plumber,
developers and supply companies; meaning that the end users were
frequently an afterthought, when they should be of primary
importance.
Resolved: to note the
contributions to the review.