Having considered an open officer report, and a presentation by the Cabinet
Member for Housing, Councillor Paul Bell, the Mayor and Cabinet agreed that:
(1) the programme update provided for the Council’s housebuilding
programme be noted;
(2) Burnt Ash Garages and Mill Gardens Garages be removed from the
Building for Lewisham Programme;
(3) the schemes at Drakes Court, Evelyn Community Centre, Former Fairlawn
Nursery Annexe, Greystead Road, Hensford Gardens, Markwell Close and
Walsham Road Garages be added to the Building for Lewisham Programme;
(4) Drakes Court, Greystead Road, Hensford Gardens and Markwell Close
proceed from RIBA Stage 1 completion to construction contract tender;
(5) Fairlawn Nursery Annex and Walsham Road garages proceed from RIBA
1 completion to construction contract tender subject to the scheme viability
meeting the required financial hurdles at completion of RIBA Stage 2;
(6) this report is accompanied by a Part 2 report outlining the financial
parameters of the programme as well as requests for additional spend
required in order to take the schemes forward;
(7) progress in relation to the new governance processes and procedures
which will be used to monitor the programme be noted;
(8) authority be delegated to the Executive Director for Housing Regeneration
and Environment to initiate and carry out any s105 consultation required for
schemes within the Building for Lewisham programme, at the appropriate
time;
(9) responses to any s105 consultation be referred back to Mayor and Cabinet
for consideration and approval to continue with the development;
(10) authority be delegated to the Executive Director for Housing,
Regeneration and Environment to approve the submission of proposals for
planning permission and discharge of conditions, non-material amendments
and section 73 applications, where applicable, for approved schemes within
the Building for Lewisham Programme and authorises the Executive Director
for Housing, Regeneration and Environment to instruct Lewisham Homes to
act on behalf of the Council with respect to all of the above, subject to
approval to continue with the development being given by Mayor and Cabinet
following consideration of any s105 consultation required;
(11) officers will return to Mayor and Cabinet to approve the allocation of
budgets for the purpose of commencement of construction work;
(12) the allocation of funding which will be used by Lewisham Homes to
appoint a contractor to deliver construction works for 32 new homes be
approved at the scheme known as Mayow Road, further details of which are
included in Part 2;
(13) the allocation of funding which will be used by Lewisham Homes to
appoint a contractor to deliver construction works for 6 new homes be
approved at the scheme known as Canonbie Road, further details of which
are included in Part 2; and
(14) the procurement strategy adopted by Lewisham Homes and the tender
analysis they have undertaken to progress Mayow Road and Canonbie Road
to this point be noted.
Publication date: 10/07/2020
Date of decision: 09/07/2020
Decided at meeting: 09/07/2020 - Mayor and Cabinet
Accompanying Documents: