Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
Having considered a confidential officer report, and a presentation by the
Mayor, the Mayor and Cabinet for the reasons set out in the report by a vote
of 10-0:
RESOLVED that:
(1) the work programme be endorsed as part of its early commitment to the
aims of the Catford Masterplan;
(2) officers be authorised to undertake a procurement exercise to find a
suitable contractor for the works, using the process set out;
(3) a waiver of the Council’s Contract Procedure Rules be approved and a
contract be awarded to ig9 to be appointed as the Employer’s Agent and
Design Team to provide technical assistance and fulfil CDM regulations with
the delivery of this project, RIBA stages 4-7 (tender preparation through to
project completion) at a total stated cost
Publication date: 12/03/2020
Date of decision: 11/03/2020
Decided at meeting: 11/03/2020 - Mayor and Cabinet
Accompanying Documents: